Events
May 15, 2025:Official opening of the biogas plant
28 February – 15 May 2025:Start-up, performance tests of biogas plant, electricity connection
April – December 2024 - Execution of biogas plant
November 28 2023 – March 19th 2024:Procurement of biogas plant
May-November 2023:Specifications for constructions of biogas plant established together with technical project designer and consultant for coordinating the implementation of the technical project
June 06 2023:All approvals and agreements for the construction of the biogas plant have been obtained
February 07, 2023The photovoltaic system started producing electricity
January 2nd 2023:Start for the installation of the photovoltaic system on the roofs of the building from ULST campus
December 5th 2022:Signing the execution contract for the photovoltaic system
May 27, 2022: Workshop and launch event of the project supported by Norway through Norway Grants, within the "Energy Program in Romania". Established project acronym: RES-CIRCULAR, project logo published on the project website
April - May 2022: Procedure for procuring the service for communication activities
April 21, 2022: Issued town planning certificate
January 25, 2022: Signing the contract for the elaboration of technical-economic and legal documents. administrative documentation as well as technical assistance within the project
June - December 2021: Procedure report, analysis, simplification of procedures, re- publication of the documentation for the three attempts to purchase services for technical project and technical assistance
June 8, 2021: Feasibility study issued
April - May 2021: Delivery of information and documents necessary for the issuance of the feasibility study
February - March 2021: Service procurement procedure for feasibility study
January - February 2021: Contracting consultancy for procurement procedures
21.12.2020Grant signed between BUASVM and Norway Grants
September - December 2019: Re-negotiating partnerships in the project, assuming the entire responsibility of the project by one partner: BUASVM “King Mihai I of Romania” from Timișoara
April - September 2019: Clarifications and communications for the remodeling of the project as indicated by Innovation Norway
February-March 2019: Drafting the project proposal, clarifications and communications in order to reshape the project, as indicated by Innovation Norway